PART VIII | LESSON 34: COMMISSIONING AND ACCEPTANCE MATERIAL HANDLING ACADEMY

Lesson 34 Worksheet: Commissioning and Acceptance

Recall first, from memory. Then sort the FAT from the SAT and write the acceptance criteria in numbers. Then assemble the Riverside commissioning plan.

Recall

Answer from memory before you flip back.

Who owns the FAT, and who owns the SAT criteria? Where does each test run?

What does "statistical and sustained" mean, and why is one clean minute not a passed test?

Name the three pieces of the service model, and the one that matters most for a one-person maintenance team.

FAT / SAT Criteria Drill

Fill each cell for the two tests. Keep the ownership line straight: our firm runs the FAT, the customer owns the SAT criteria.

 FAT (factory acceptance test)SAT (site acceptance test)
Who owns it
Where it runs
What it proves
The exception path / real load
WRITE THE SAT CRITERIA IN NUMBERS

Riverside's acceptance is statistical and sustained, and stated up front as numbers. Write each criterion the way it belongs in the proposal and the contract, using only the targets the project states.

Sustained rate:
Misdirect rate:
WMS latency, under peak load:
RIVERSIDE PROJECT NOTES: THE COMMISSIONING PLAN